No Electrical Certificate? Regularisation Guide
The short answer: If past electrical work has no certificate, first work out whether it was notifiable under Part P. Repairs, replacements and additions to existing circuits away from a bath or shower are usually not. If the work was notifiable and a registered electrician did it, ask them for the certificate or trace it through their scheme. If notifiable work was never notified, you can apply to your local council for a regularisation certificate, which is building control approval after the event. The council may ask for the work to be opened up and tested, and for changes, before it signs it off. If you are selling, speak to your conveyancer before you contact the council, because approaching the council can invalidate an indemnity insurance policy.
This guide covers England. Our Part P guide explains notifiable work in full, and our guide to electrical certificates explains what an EIC, a Minor Works Certificate and an EICR each are.
First, check whether the work was notifiable
Only notifiable work has to be notified to building control. The Planning Portal lists three types in England:
- a new consumer unit (fuse box)
- a complete new circuit
- alterations in a special location, which in England means around a bath or shower
It adds that “most repairs, replacements and maintenance jobs, and alterations or additions to existing circuits outside special locations, are not notifiable.” In Wales the special locations also include kitchens and outdoors. Our Part P guide has a table of common jobs if you are not sure which side of the line yours falls.
If the work was not notifiable, building control never needed to be told, so there is no building control certificate to look for. The paper you may be missing is the electrician’s own certificate. Richmond Council’s electrical works page says non notifiable work, such as replacing accessories or adding lighting points to existing circuits, can be done by a competent person who issues a Minor Works Certificate.
Ask whoever did the work for a copy. NICEIC gives the same advice for a lost EIC or EICR: contact the contractor who did the job. If you cannot get a copy and want to know the work is safe, an electrician can inspect and test the installation and report on its condition in an Electrical Installation Condition Report (EICR). Use an electrician registered to self-certify notifiable work. Our EICR advice page explains what an inspection involves.
If a registered electrician did the work
Electricians registered with a competent person scheme can self-certify notifiable work. Under regulation 20 of the Building Regulations 2010, they must give the occupier a copy of the certificate and notify building control within 30 days of finishing the work. The Planning Portal says you should also get an Electrical Installation Certificate (EIC), which is a separate document.
If the certificate never arrived, or you have lost it, work through these in order.
- Ask the electrician. This is the usual route for the EIC or Minor Works Certificate. checkmynotification.com says EICs and EICRs come from the electrician, not from its service.
- Search checkmynotification.com if the electrician was with NICEIC or ELECSA. The site is run by NICEIC and ELECSA and only covers Building Regulations compliance certificates for work by their contractors. You can buy a copy there. It warns that “we may not have notifications over 6 years old”.
- Contact the scheme if the electrician was registered with a different one. GOV.UK says you can check an electrician on the Electrical Competent Person Register. Our guide to choosing a qualified electrician covers what else to check.
If none of this turns anything up, the work may never have been notified. That is where regularisation comes in.
What regularisation is
Regularisation lets the owner apply for building control approval for work that has already been done. GOV.UK calls it retrospective approval.
- It comes from regulation 18 of the Building Regulations 2010.
- Only the local authority can deal with it. GOV.UK says registered building control approvers cannot.
- It only covers work done on or after 11 November 1985.
- If the council is satisfied, it may issue a regularisation certificate. The regulation says this is “evidence (but not conclusive evidence)” that the work complies.
The third party certifier route described in our Part P guide has to be arranged before work starts, so it does not help with work that is already done.
What regularisation involves
The application. You fill in the council’s form and pay its charge. Richmond’s regularisation page asks for plans showing the completed work and the original layout. Kingston’s regularisation page asks for supporting documents such as site plans, calculations, invoices or photos. For electrical work, gather what you have: who did the work, roughly when, and any invoices or photos taken before walls were closed up. The Planning Portal advises contacting the council before you apply.
The inspection. Regulation 18 lets the council ask you to take reasonable steps, “including laying open the unauthorised work for inspection by the authority, making tests and taking samples”. Richmond says its inspection may involve “opening up of the works, carrying out tests and/or sampling”. Kingston says it may ask for work to be uncovered, and that you must book a site inspection before it can issue a certificate.
The testing. Richmond’s electrical works page says that where building control, rather than a scheme member, signs off electrical work, it wants the installer’s test certificate and a certificate from an independent competent person. That page covers the building control route in general. Its regularisation page does not name a particular report, so ask the council what it will accept before you book any testing.
The outcome. Under regulation 18 the council tells you one of three things: what work is needed to make it comply, that it cannot decide, or that no work is needed. GOV.UK says you might need to make alterations before the council agrees the work complies. The Planning Portal says “exposure, removal and/or rectification of works may be necessary”.
For the testing and any remedial work, use an electrician registered to self-certify notifiable work, and agree with the council what it needs before work starts.
What regularisation costs
Each council sets its own charges, and the Planning Portal says fees vary. The figures below are the councils’ own, not our prices. If you live in Kingston or Richmond, this is what the two councils publish.
Richmond Council. Its Building Regulations Charges Scheme No. 1 2026, with base charges effective from 1 April 2026, lists a regularisation charge of £601 for “electrical wiring up to 12 circuits” where the electrician is not in a competent person scheme. The scheme gives a typical four bedroom house as the example for that size of job. It sets the regularisation charge at 120% of the building notice charge and says all its charges are subject to VAT except regularisation, so no VAT is added to the £601. On refunds, Richmond’s regularisation page says that since April 2010 it has considered refunds for abandoned projects based on the costs it has already incurred, with a minimum £50 admin charge.
Kingston Council. Kingston lists its regularisation charge for electrical installations on its standard domestic charges page. The page does not show when its figures took effect, so check the current charge with the council. Kingston’s regularisation page says that if you withdraw, “you’ll not receive a refund of any part of the charge”.
For any other council, check its building control charges page before you apply.
The council’s charge is only part of the cost. You also pay for any opening up, testing and alterations, and for making good afterwards. Those costs depend on what is found.
Can the council still take action?
GOV.UK says you may have to correct the work or pay a fine if building regulations are not followed.
The time limit for one kind of enforcement has changed. Under section 36 of the Building Act 1984, a council can serve a notice over work that breaks the building regulations. As amended by the Building Safety Act 2022, in force in England from 1 October 2023, the Act says “a section 36 notice shall not be given after the expiration of 10 years from the date of the completion of the work”. Before that change, the limit was 12 months.
How the new limit applies to work finished before 1 October 2023 depends on transitional rules. If it matters to a sale or a dispute, ask a solicitor.
Selling a home with missing certificates
The Homeowners Alliance sets out three options when building regulations approval is missing: get a copy of the certificate, apply for regularisation, or take out indemnity insurance.
Indemnity insurance and regularisation pull in opposite directions. The Homeowners Alliance advises against contacting the council if you are unsure, and says policies become invalid if anyone approaches the council. Solicitors Trethowans (June 2024) add that:
- these policies cover enforcement action only, not the quality of the work
- a previous refusal by the council will typically void cover
- future building work may invalidate the policy
Trethowans also advise getting a survey. Check the terms of any policy you are offered.
Speak to your conveyancer before anyone contacts the council. Bear in mind that an insurance policy says nothing about whether the wiring is safe. If you are buying, an EICR from an electrician registered to self-certify notifiable work tells you about the condition of the installation. Our guide to getting an EICR when buying a house explains how that works.
What this means for you
- The work was not notifiable. Ask whoever did it for their Minor Works Certificate or EIC. If you cannot get one, an EICR will tell you the condition of the installation.
- A registered electrician did notifiable work. Ask them first, then try checkmynotification.com for NICEIC and ELECSA work, or contact the electrician’s scheme.
- Notifiable work was never notified. Apply to your local council for regularisation. Ask the council what testing it wants, and use an electrician registered to self-certify notifiable work for the testing and any remedial work.
- You are selling or buying. Talk to your conveyancer before contacting the council, and weigh up regularisation against indemnity insurance.
We don’t carry out notifiable work or EICRs. For general advice about the electrics in your home, get in touch and we will point you in the right direction.
Sources
- legislation.gov.uk, The Building Regulations 2010, regulation 18 and regulation 20 (checked 23 November 2026)
- legislation.gov.uk, Building Act 1984, section 36, as amended by the Building Safety Act 2022 (in force in England from 1 October 2023; checked 23 November 2026)
- GOV.UK, Building regulations approval: How to apply and Use a competent person scheme (checked 23 November 2026)
- Planning Portal, Electrics: building regulations general information and Regularisation (checked 23 November 2026)
- NICEIC and ELECSA, checkmynotification.com (checked 23 November 2026)
- NICEIC, How to work with your tradesperson (checked 23 November 2026)
- London Borough of Richmond upon Thames, Building Regulations and electrical works and How to make a regularisation application (checked 23 November 2026)
- London Borough of Richmond upon Thames, Building Regulations Charges Scheme No. 1 2026 (effective 1 April 2026)
- Royal Borough of Kingston upon Thames, Apply for a regularisation certificate and Standard building control charges: domestic and residential (no date shown; checked 23 November 2026)
- Homeowners Alliance, No building regulations approval (no date shown; checked 23 November 2026)
- Trethowans, Lack of building regulation certification: why legal indemnity policies may not be the cure (June 2024)
Frequently asked questions
What should I do if past electrical work in my home has no certificate?
First check whether the work was notifiable under Part P. In England only three types of job are: a new consumer unit, a new circuit, and alterations around a bath or shower. If a registered electrician did notifiable work, ask them for the certificate or trace it through their scheme. If notifiable work was never notified, you can apply to your local council for a regularisation certificate. If you are selling, speak to your conveyancer before you contact the council.
What is a regularisation certificate?
It is building control approval given after the work was done. It comes from regulation 18 of the Building Regulations 2010, is only available from the local authority, and only covers work done on or after 11 November 1985. The council may ask for the work to be uncovered and tested, and for changes, before it issues one. The law says the certificate is evidence, but not conclusive evidence, that the work complies.
How much does regularisation cost for electrical work?
Each council sets its own charges. Richmond Council's Building Regulations Charges Scheme No. 1 2026, effective from 1 April 2026, lists £601 to regularise electrical wiring of up to 12 circuits where the electrician is not in a competent person scheme, with no VAT on the regularisation charge. These are the council's figures, not ours. The cost of opening up, testing and any alterations is on top.
How do I find a lost Building Regulations compliance certificate?
Ask the electrician first. If they were with NICEIC or ELECSA, you can search checkmynotification.com and buy a copy, though the site says it may not have notifications over 6 years old. For work registered through another scheme, contact that scheme.
Can the council still take action over old electrical work?
In England, since 1 October 2023, the Building Act 1984 says a section 36 notice cannot be given more than 10 years after the work was completed. Before that the limit was 12 months. How the change applies to work finished before October 2023 depends on transitional rules, so take legal advice if it matters to you.
Is indemnity insurance an alternative to regularisation?
It can be, but the two pull in opposite directions. The Homeowners Alliance says a policy becomes invalid if anyone approaches the council. Solicitors Trethowans say these policies cover enforcement action only, not the quality of the work. An insurance policy does not tell you whether the wiring is safe, so speak to your conveyancer before deciding.