EIC vs Minor Works vs EICR: Electrical Certificates Explained
The short answer: An Electrical Installation Certificate (EIC) is what you should get after new electrical work, such as a rewire, a new circuit or a new consumer unit. A Minor Electrical Installation Works Certificate (usually called a Minor Works Certificate) covers smaller jobs that do not add a new circuit, like adding a socket or moving a light switch. An Electrical Installation Condition Report (EICR) is different: it is a report on the condition of an existing installation, not a certificate for new work. Keep all three in a safe place for as long as you own the home, and pass them on when you sell.
Here is what each one is, when you should receive it, what to check before you file it away, and how long to keep it.
The three documents at a glance
| Electrical Installation Certificate (EIC) | Minor Works Certificate (MEIWC) | Electrical Installation Condition Report (EICR) | |
|---|---|---|---|
| What it is for | New installations, new circuits and consumer unit replacements | Additions and alterations that do not include a new circuit | Checking the condition of an existing installation |
| Typical examples | A full rewire, solar panels, a new circuit, a new consumer unit | An extra socket on an existing circuit, moving a light switch, replacing a light fitting | A periodic check, a landlord’s five-yearly check, or a check before buying |
| Who signs it | The people responsible for design, construction, and inspection and testing (one person can sign all three) | One person, for design, construction, and inspection and testing | The person or people who carried out the inspection and testing |
| What it tells you | The new work met BS 7671 when it was completed | The minor work met BS 7671 and did not impair the safety of the existing installation | Whether the installation is satisfactory or unsatisfactory for continued use, and why |
All three are based on the model forms published by the Institution of Engineering and Technology (IET) for BS 7671, the UK wiring regulations. The current versions were issued for BS 7671:2018+A4:2026. Scheme bodies such as NICEIC and NAPIT issue their own branded versions, so yours may look different, but the content should be the same.
Electrical Installation Certificate (EIC)
What it is
The IET’s guidance printed on the EIC says it confirms that the electrical work it covers “has been designed, constructed, inspected and tested in accordance with BS 7671”. It is only for new work. The same guidance says it “can not be used for the inspection and testing of an existing electrical installation”.
When you should get one
According to the NICEIC Help Hub, you should receive an EIC if the job involved a new circuit or the installation of a new consumer unit or distribution board. NICEIC gives a rewire and a solar panel installation as examples.
The certificate records which kind of work it covers. NICEIC explains the three options:
- New installation: the whole installation is new, for example after a complete rewire.
- Addition: one or more new circuits have been added to an existing installation.
- Alteration: existing circuits have been modified or extended, or equipment such as the consumer unit has been replaced.
An electrician may also choose to issue one EIC instead of several Minor Works Certificates when more than one existing circuit has been added to or altered. The IET form allows for this, and NICEIC mentions it too.
What to check on an EIC
- Your address and the description of the work. Section B should say what the certificate covers and whether it is a new installation, an addition or an alteration.
- Three signatures. Section C has separate declarations for design, construction, and inspection and testing. The IET notes say one authorised person can sign in each place, and a single-signature version of the form also exists.
- The schedules. The IET says the certificate is only valid if the schedule of inspections has been completed and the schedules of circuit details and test results are attached. The pages should be numbered with the total number of pages shown.
- The recommended next inspection. Section D gives the maximum interval the designer recommends before the installation is next inspected and tested.
- Dates that make sense. NICEIC says the dates on a certificate must align with the date the job was completed.
- Any departures from BS 7671. Each signatory can list departures from the regulations. If anything is listed, ask what it means.
Minor Electrical Installation Works Certificate (MEIWC)
What it is
The IET’s model form is headed “To be used only for minor electrical work which does not include the provision of a new circuit”. The notes on the form give examples: adding sockets or lighting points to an existing circuit, or moving a light switch. It can also be used for replacing accessories or light fittings, “but not for the replacement of consumer units, distribution boards or similar items”.
The declaration on the form confirms that the work does not impair the safety of the existing installation and was designed, constructed, inspected and tested in accordance with BS 7671.
When you should get one
NICEIC says you would expect a Minor Works Certificate if you had a light fixture repaired, a power socket moved or installed, or a circuit breaker or fuse replaced. It also says you should receive one for each existing circuit that has been added to or altered. The IET’s guidance on the form says the same.
What to check on a Minor Works Certificate
- The description of the work. It should match what you asked for.
- The circuit. Section C identifies the circuit that was altered or extended, and Section D records the test results for it.
- Comments on the existing installation. The electrician can note defects they saw in the rest of your installation. Read these.
- One certificate per circuit. If work was done on two circuits, you should have two certificates, or one EIC covering both.
- The right type of certificate. The IET’s guidance on the form says it is not appropriate if you asked for more extensive work, “for which you should have received an Electrical Installation Certificate”. If you had a new circuit or a new consumer unit and only received a Minor Works Certificate, ask why.
Electrical Installation Condition Report (EICR)
What it is
An EICR is a report, not a certificate. The IET’s guidance for recipients says its purpose is to confirm, “so far as reasonably practicable”, whether the electrical installation is in a satisfactory condition for continued service at the date it was inspected and tested. NICEIC describes it as a health check of an existing installation that identifies signs of age, wear and tear, and damage. You may also hear it called a periodic inspection report (PIR).
When you get one
- Owner-occupiers. NICEIC says there is no law requiring homeowners to have an EICR, but it is generally recommended at least once every 10 years. The date for the next inspection on your last EICR or EIC is also a good guide.
- Landlords. In England, the government’s guidance says landlords must have the installation inspected and tested at least every five years and obtain a report, usually an EICR. The rules were extended to the social rented sector in 2025, with the duties applying to existing social tenancies from 1 May 2026. Our guide to EICR requirements for landlords has more detail.
- Buyers. An EICR is a common step before exchange. See EICR when buying a house.
Satisfactory, unsatisfactory and the codes
Each problem the inspector finds is given a code. The IET’s guidance for recipients explains them:
- C1 (Danger present): the safety of people using the installation is at risk, and remedial work is recommended immediately.
- C2 (Potentially dangerous): safety may be at risk, and remedial work is recommended as a matter of urgency.
- C3 (Improvement recommended): remedial work may improve safety, but a C3 is advisory only.
- FI (Further investigation): the inspector found a potential issue but cannot give it a code until it has been investigated further.
The overall assessment is unsatisfactory if any observation is coded C1 or C2. C3 and FI observations do not, on their own, make a report unsatisfactory. The IET form also notes that an installation designed to an earlier version of the wiring regulations, which does not fully comply with the current version, “is not necessarily unsafe for continued use, or require upgrading”.
What to check on an EICR
- The reason for the report (Section B) and the dates of the inspection.
- Extent and limitations (Section D). This says which parts of the installation were inspected and what was not. Unless agreed otherwise, cables hidden in walls, under floors, in roof spaces or underground are not inspected. Any rooms or equipment the inspector could not get to should be listed here too.
- The overall assessment (Section E): satisfactory or unsatisfactory.
- The observations and codes (Section K), with the location of each problem.
- The recommended date for the next inspection (Section F), with the reasons for it.
- The schedules. The IET says the report is only valid if the schedules of inspections, circuit details and test results are attached.
After remedial work
If an EICR finds problems and they are put right, you do not usually get a new EICR. NICEIC says the business that did the remedial work should provide an appropriate certificate for it (an EIC or a Minor Works Certificate) rather than a new satisfactory report. For landlords in England, the government’s guidance accepts a satisfactory EICR, an EIC or a Minor Works Certificate as written confirmation that remedial work has been done.
The other certificate: Building Regulations compliance
An EIC or Minor Works Certificate shows the work met BS 7671. It is not the same as Building Regulations sign-off.
In England, some electrical work in homes is notifiable under Part P of the Building Regulations. Approved Document P lists it as:
- installing a new circuit
- replacing a consumer unit
- any addition or alteration to existing circuits in a special location, which means the space around a bath or shower
For notifiable work you should receive a second document:
- A Building Regulations compliance certificate if the work was done by an electrician registered with a competent person scheme, such as NICEIC or NAPIT. NAPIT says you should receive this “in addition to the EIC/MEIWC”. GOV.UK notes it will also show up in solicitors’ searches when you sell.
- A completion certificate (or final certificate) from building control if the work was notified to them instead.
GOV.UK warns that without approval “you will not have the certificates of compliance you may need when you want to sell your home.” Our guide to choosing a qualified electrician explains how to check whether an electrician is registered with a scheme.
How long to keep them
There is no fixed retention period for homeowners, but the guidance points one way: keep them for as long as you own the property.
- EIC and Minor Works Certificates. The IET’s guidance on both forms says the original should be “retained in a safe place and be shown to any person inspecting or undertaking further work on the electrical installation in the future”. If you move, the certificate shows the new owner that the work complied with BS 7671 when it was issued.
- EICRs. The IET says an EICR “is an important and valuable document which should be retained for future reference”. If the property changes hands, it gives the new owner or occupier details of the installation’s condition at the time.
- Building Regulations certificates. NICEIC says you may be asked for your EIC, Minor Works and Building Regulations certificates when selling or renting out your home. It also points out that certificates provide a basis for future inspection and testing, and can be evidence that an installation was installed safely if there is ever a claim.
- Landlords. In England, landlords must keep a copy of the report until the next inspection is due (or carried out, if later), and give a copy to the inspector who does the next one, according to the government’s guidance.
If you have lost a certificate, ask the business that did the work for a copy. For lost Building Regulations compliance certificates, NICEIC points to checkmynotification.com, where notified work can be searched and duplicates bought. For work registered through another scheme, contact that scheme. If you cannot trace a certificate for notifiable work, our guide to electrical work with no certificate explains what to do next, including building control regularisation.
While you have the paperwork out
The IET’s guidance on all three forms includes a simple instruction: if your installation has an RCD, test it every six months by pressing the button marked “T” or “Test”. It should switch off the supply, and you then switch it back on. If it does not switch off, seek expert advice. If you have an arc fault detection device (AFDD) with a test button, the IET says to test that every six months too, following the manufacturer’s instructions if it also tests itself automatically.
If the problem is the opposite and something keeps tripping, our guide to why a fuse box keeps tripping explains the common causes, and our fault finding page covers how faults are traced.
What this means for you
- Had new work done? Check you received the right certificate (EIC or Minor Works), that it is signed and has its schedules, and, for notifiable work, that a Building Regulations certificate follows.
- Not sure when the installation was last checked? Look for the next inspection date on your most recent EIC or EICR. Our EICR advice page explains what an inspection involves.
- Buying a home? Ask the seller for any EICs, Minor Works and Building Regulations certificates, and read about getting an EICR when buying a house.
- Thinking about a bigger job? Our guides to replacing an outdated consumer unit and house rewiring explain what is involved. Both are notifiable and should come with an EIC.
For inspections, certificates and any notifiable work, use an electrician registered with a competent person scheme. If you have a question about a certificate or report you have been given, get in touch for general advice.
Sources
- IET, BS 7671 model forms for BS 7671:2018+A4:2026: Electrical Installation Certificate, Minor Electrical Installation Works Certificate and Electrical Installation Condition Report, including the notes and guidance for recipients
- NICEIC, Householders and landlords help hub
- NICEIC, How to work with your tradesperson
- NICEIC, Electrical Installation Condition Reports (EICRs)
- NAPIT, Consumer advice for households
- GOV.UK, Electrical safety standards in the private and social rented sectors: guidance (November 2025)
- GOV.UK, Electrical safety: Approved Document P (2013 edition, sections 2 and 3)
- GOV.UK, Building regulations approval and Use a competent person scheme
Frequently asked questions
What is the difference between an EIC and an EICR?
An Electrical Installation Certificate (EIC) is issued when new electrical work is completed, such as a rewire, a new circuit or a new consumer unit. It confirms the work was designed, built, inspected and tested to BS 7671. An Electrical Installation Condition Report (EICR) is a report on the condition of an existing installation. The IET's own guidance on the EIC says it cannot be used for inspecting an existing installation, and an EICR should be issued for that.
Is a Minor Works Certificate enough for a new consumer unit?
No. The IET's model Minor Works form says it is for work that does not include a new circuit, and that it is not for replacing consumer units, distribution boards or similar items. NICEIC says you should receive an EIC if the job involved a new circuit or a new consumer unit.
Do I get a separate certificate for Building Regulations?
For notifiable work, yes. Notifiable work includes a new circuit, a consumer unit replacement, and additions or alterations to circuits in the area around a bath or shower. As well as the EIC or Minor Works Certificate, you should receive a Building Regulations compliance certificate if a registered competent person did the work, or a completion certificate from building control if the work was notified to them.
How long should I keep electrical certificates?
There is no fixed retention period for homeowners. The IET's guidance printed on each form says the original should be kept in a safe place and shown to anyone inspecting or working on the installation in future, and that it shows a new owner the work met BS 7671 when it was issued. In practice that means keeping them for as long as you own the property and passing them on when you sell. Landlords in England must keep the electrical safety report at least until the next inspection is due.
Do homeowners need an EICR by law?
No. NICEIC says there is no law requiring owner-occupiers to have an EICR, but it is generally recommended at least once every 10 years. Landlords are different: in England, privately rented homes, and now social rented homes too, must have the electrical installation inspected and tested at least every five years.
What should I do if I never received a certificate?
Ask the business that did the work first. NICEIC says you should expect a fully completed certificate shortly after the job is finished, and if you have not received it within a month, you can use its complaints procedure. For a Building Regulations compliance certificate from a NAPIT member that has not arrived, NAPIT says to contact its customer services team.
Need lighting control, a smart home upgrade or an electrical fault tracked down? Tell us what you need.